|
|
Jessup-Bould Limited |
|
|
|
Energy from Waste (Gasification) |
|||
|
|
|||
|
Project Background |
Client:
Planet Advantage Limited |
||
|
Jessup-Bould
Limited provided technical support to Planet Advantage Limited during the pre-design
phases of this project which uses Enerwaste technology. The plant has now
been constructed at Scotgen’s Dargavel site in |
|||
|
|
|
|
Process Description The plant is comprised of 2 waste processing
and heat recovery streams with a common steam turbine driven alternator. Each stream has four gasification
chambers sequenced to operating on a programmed cyclic basis and provide a
constant flow of synthesis gas to a common (one per stream) oxidation
chamber. When a gasification chamber becomes available the operator opens the hydraulically driven front and rear doors. |
|
|
The operator de-ashes the chamber by
use of a front end loader with pusher tool onto the de-ashing conveyor at the
rear of the chamber. When the chamber has been emptied,
the operator closes the doors. To charge the gasification chamber, the operator opens the hydraulically driven charge door in the roof of the chamber. The front end loader is used to charge the chamber with feedstock material. A top side operator monitors filling and advises the front end loader driver as required to achieve an even distribution in the chamber to the working level. |
|
|
On completion of charging, the
operator closes the charge door. The operator initiates the chamber
start up sequence. Provided that the temperature in the oxidation chamber is
above the minimum required by WID (the Waste Incineration Directive), the
sequence ignites the material in the gasification chamber using the gas oil
fired burner. Flue gas generated during
start up to flow through the refractory lined syngas duct to the oxidation
chamber. |
Courtesy of Enerwaste |
|
Once combustion
of the feedstock has been established oil firing is terminated and the
chamber undergoes sub-stoichiometric gasification. The resulting synthesis
gas flows through the established route to the oxidation chamber. A
temperature controller in the outlet duct from the chamber will vary the
speed of the chamber’s dedicated gasification air fan to control the
gasification reaction. Air for the process is drawn from within the process
hall. Waste
heat is recovered from the oxidation chamber flue gases by raising steam in a
boiler. This steam is used in the common turbine alternator to generate
electricity for house use and export to the grid. Condensate
is recovered for reuse as boiler feed water. Flue
gas leaving the boiler is cleaned by dry scrubbing with PAC / Sodium
Bicarbonate and a bag filter. Continuous emissions monitoring is used to control to Sodium Bicarbonate dosing rate and to ensure that the plant meets regulatory requirements. |
|
|
|
|
|
Responsibilities Technical
discussions with prospective detailed engineering design contractors. Mass end
energy balance verification (including site performance testing): Supply
and modification of laboratory equipment for gas sampling. Gas
sampling and analysis for mass and energy balance purposes. |
|
|
The initial contribution to this project was the assessment
of the nominated detailed design contractor. This mainly centred on resolving
discrepancies in the mass and energy balances provided by the technology
provider and those from the contractor. Although the contractor had
undertaken gas sampling at a demonstration plant for batch-wise processing of
waste in In the original set of tests, the contractor had arranged
for around ten gas samples to be sent to the The Orsat was deployed at site following a period of
in-house training with a tailor made gas ‘cocktail’ and equipment
modification in the The availability of analysis ‘on-demand’ more than tripled
the number of readings taken at the initial testing. Furthermore, a
structured sampling and data logging procedure was prepared that enabled
meaningful data to be acquired in order to derive a series of mass balances
for each batch gasified. Although the demonstration plant had no other means
of monitoring energy generated from the waste, these performance tests
enabled the energy release rate to be calculated using mass balance results. Issues over this contractors quoted scope of supply meant
that an alternative contractor was sought. JBL assisted with the technical
assessment of Planet Advantages alternative contractors’ short list. Following appointment of the detailed design contractor,
there followed a transitional period during which the findings of the site
tests were reported and handed over for use in the detailed design. |
|
Project Value (Feb 2007) £
18,000,000 Unit Operations Batch
gasification chambers. Combustion. Fans. Boilers. Steam
turbine / Condenser Dry flue
gas scrubbing. Cooling
tower. |
Hazards (Site testing) Waste;
combustible and pathogenic solids. Fuels
(gas oil). Gases arising
from process (CH4, CO, H2). Hazardous
analytical reagents (Conc. H2SO4, KOH, NaOH, etc). Hot
gases, surfaces and materials. Moving
heavy plant. Rotating
machinery. Liaison Prospective
Detailed Process Design Contractors |